
Sizing a generator by adding up nameplate wattage works only when every load behaves the same way. Real facilities do not work like that. Motors draw far more current at startup than at full speed, VFDs and UPS systems reshape the current waveform, and lightly loaded equipment drags power factor down when demand drops. The result is a load profile whose power factor changes throughout the day, and a generator that was sized on kilowatts alone can trip, overheat, or lose voltage control even though the math looked fine on paper. This guide walks through a sizing method built for mixed and variable power factor loads (with the formulas), an example, and an interactive generator sizing calculator you can use to run your own numbers.
Why Power Factor Changes the Sizing Math
Generators carry two ratings that must both be respected. Let’s take a look at kW to kVA generator sizing. The engine limits real power in kilowatts (kW), the work your equipment performs. The alternator limits apparent power in kilovolt-amperes (kVA), the total current it can push through its windings. Power factor is the ratio between the two, and industrial three phase generators are rated at 0.8 power factor as the standard design point. A 500 kVA generator delivers 400 kW at 0.8 PF. If your facility operates at a lower power factor than the rating, the alternator runs out of current capacity before the engine runs out of power, and the usable output drops below the nameplate kW. For a full refresher on the definition and formulas, see our guide to generator power factor.
The sizing problem gets harder when power factor is not one fixed number. That is the case in almost every commercial and industrial facility, because different load types pull the composite power factor in different directions:
- Motors during starting. An across the line motor start draws 5 to 7 times running current at a power factor as low as 0.2 to 0.4. For a few seconds the alternator sees a huge, almost entirely reactive demand.
- Lightly loaded motors. A motor running at 25 percent load can operate at 0.6 power factor or worse, even though the same motor at full load runs near 0.85.
- VFD driven equipment. Variable frequency drives present a high displacement power factor, often 0.95 or better, but they draw distorted, harmonic rich current that heats alternator windings and confuses voltage regulation.
- UPS and IT loads. Modern double conversion UPS systems and server power supplies can present near unity or even leading power factor. A leading power factor beyond roughly 0.9 can push the alternator’s automatic voltage regulator toward instability.
- Cyclical process loads. Welders, compressors, crushers, and conveyors cycle between heavy and light demand, so the composite power factor of the facility swings with the production schedule.
Because of these swings, a correct sizing exercise checks the generator against the worst credible combination of kW demand, kVA demand, and starting events rather than a single average number.
The Five Step Sizing Method for Mixed Power Factor Loads
Step 1: Inventory every load with its own power factor.
List each significant load or load group with its running kW and its power factor at the loading level it will really see. Use measured data where possible. A clamp on power meter reading at the service entrance during peak production is worth more than any nameplate. Where you must estimate, the typical power factor table in our generator power factor guide lists realistic values by load type, and the calculator below includes the same estimates as presets.
Step 2: Convert each load to kVA and kVAR, then combine correctly.
Loads at different power factors cannot simply be added in kVA. Calculate each load’s apparent and reactive power, then sum the real and reactive components separately and recombine them:
- kVA per load = kW divided by PF
- kVAR per load = the square root of (kVA squared minus kW squared)
- Total kVA = the square root of (total kW squared plus total kVAR squared)
- Composite PF = total kW divided by total kVA
This vector method usually produces a smaller, more accurate kVA total than dividing the whole facility’s kW by 0.8, because high power factor loads like lighting and IT equipment offset the reactive demand of the motors.
Step 3: Check the largest motor start.
Identify the largest motor that starts across the line and estimate its starting kVA, typically 5 to 6 kVA per horsepower for common NEMA code letters. The alternator must supply that inrush, on top of whatever is already running, without letting voltage dip below what your equipment tolerates. Many specifications limit dip to 15 to 20 percent. Motor starting, not running load, is what drives alternator size in many compressor, pump, and HVAC heavy facilities. Soft starters and VFDs reduce starting kVA dramatically and can allow a smaller generator.
Step 4: Account for nonlinear loads and leading power factor.
When VFDs, UPS systems, and switch mode power supplies make up a large share of the load, plan for an oversized alternator or a genset the manufacturer has rated for nonlinear duty, because harmonic currents heat windings beyond what the kVA number implies. If UPS input filters or long cable runs can push the system capacitive at light load, confirm with the manufacturer that the voltage regulator will remain stable, and consider load management that keeps some lagging load online. Our power factor guide covers lagging versus leading power factor and the regulator limits in detail.
Step 5: Apply reserve margin and check both ratings.
Add roughly 25 percent reserve to the running kW total to cover future loads, altitude and temperature derating, and healthy operating headroom, then round up to the next standard genset size. Confirm the selection two ways: the engine kW rating must exceed your margined kW demand, and the alternator kVA rating must exceed both your total running kVA and the motor starting requirement. Verify the duty rating as well, since standby, prime, and continuous ratings carry different load limits. Our diesel generator sizing FAQ covers the audit and reserve capacity basics in more detail.
Worked Example: A Mixed Load Facility
Consider a light manufacturing facility with four load groups:
- Process motors including a 40 hp air compressor: 33 kW at 0.85 PF, which is 38.8 kVA and 20.4 kVAR
- HVAC equipment: 60 kW at 0.87 PF, which is 69.0 kVA and 34.0 kVAR
- LED lighting and receptacles: 25 kW at 0.95 PF, which is 26.3 kVA and 8.2 kVAR
- UPS fed IT room: 40 kW at 0.99 PF, which is 40.4 kVA and 5.7 kVAR
The totals are 158 kW and 68.3 kVAR. Total kVA is the square root of (158 squared plus 68.3 squared), which is about 172 kVA at a composite power factor of 0.92. Notice the difference in method: dividing 158 kW by the standard 0.8 rating would suggest 198 kVA of demand, while the vector calculation shows the facility really draws about 172 kVA, because the lighting and IT loads offset part of the motor reactive demand.
Sizing is not finished yet. With 25 percent reserve, the kW requirement becomes about 198 kW, which points to a standard 200 kW genset rated 250 kVA at 0.8 PF. The final check is the 40 hp compressor. Started across the line, it demands roughly 200 to 240 starting kVA for a few seconds. A 250 kVA alternator will typically ride through that with acceptable voltage dip, but the exact answer depends on the alternator’s transient curves, so confirm the start with the manufacturer’s sizing data or fit a soft starter. In this example, motor starting nearly consumed the entire alternator rating, which is exactly why skipping Step 3 is the most common sizing mistake in motor heavy facilities.
Run Your Own Numbers: Multi Load Sizing Calculator
Generator Load Worksheet
Add each load with its own power factor. Totals, composite power factor, and a recommended generator size update as you type.
Your Totals
This worksheet provides estimates for planning purposes only. It should not be used as a final sizing specification. Site conditions, altitude, harmonic content, and duty rating all influence the correct selection. Contact Depco Power Systems for a sizing consultation.
The generator size calculator in our generator power factor guide converts single values between kW, kVA, and power factor. The worksheet above does the harder job: enter each of your loads with its own power factor, and it combines them with the vector method, checks your largest motor start, applies reserve margin, and recommends a standard generator size in both kW and kVA. The worksheet provides an estimate for planning purposes. Site conditions, altitude, fuel type, harmonic content, and duty cycle all influence the final selection, so treat the output as a starting point for a conversation rather than a purchase specification. For one line unit conversions between kW, kVA, amps, and horsepower, our power calculators page remains available.
When to Bring in a Load Study
If your facility includes large across-the-line motor starts, a high proportion of VFD or UPS load, medical or life safety circuits, or expansion plans, a metered load study is the reliable path to a correct answer. Depco Power Systems can review your load data, run manufacturer sizing software against candidate units, and match the result to available equipment.
Browse our inventory of industrial diesel gensets or natural gas generator sets, or contact us for a sizing consultation.
Frequently Asked Questions
What is a variable power factor load?
A variable power factor load is equipment, or a mix of equipment, whose ratio of real power to apparent power changes with operating conditions. Motors are the most common example: they start at a very low power factor, run near 0.85 at full load, and drop to 0.6 or lower when lightly loaded. Facilities with mixed motor, lighting, VFD, and IT loads see their composite power factor shift throughout the day as equipment cycles on and off.
Should I size a generator in kW or kVA?
Both. The engine must cover your real power demand in kW, and the alternator must cover your apparent power demand in kVA, including motor starting inrush. A generator selection is only correct when it passes both checks. Industrial three phase gensets are rated at 0.8 power factor, so a 250 kVA unit delivers 200 kW at that rating.
What power factor should I use when sizing a generator?
Use the measured or estimated power factor of each load rather than one blanket number. Combine loads with the vector method: sum kW and kVAR separately, then recombine into total kVA. Reserve the standard 0.8 figure for interpreting genset nameplates, not for describing your load.
How does motor starting affect generator sizing?
An across the line motor start draws roughly 5 to 6 kVA per horsepower for a few seconds at a very low power factor. The alternator must supply that inrush while holding voltage dip within limits, typically 15 to 20 percent. In facilities with large compressors or pumps, the starting requirement, not the running load, often determines alternator size. Soft starters, VFDs, and staged starting sequences all reduce the requirement.
Do VFDs and UPS systems change how I size a generator?
Yes, in two ways. Their harmonic currents heat alternator windings beyond what the kVA figure suggests, so generator manufacturers commonly recommend an oversized alternator or a specific nonlinear load rating when VFD and UPS equipment makes up a large share of the connected load. They can also push a lightly loaded system toward a leading power factor, which risks voltage regulator instability; our generator power factor guide explains the lagging and leading limits. Manufacturer sizing software accounts for both effects automatically.
How much reserve capacity should I add when sizing?
Add about 25 percent above your calculated running load. The reserve covers future equipment additions, derating altitude and high ambient temperatures, and keeps the generator out of continuous full load operation. Avoid oversizing far beyond that, since diesel engines that run persistently below about 30 percent load are prone to wet stacking.




